Nobody Schedules the Waiting
A customer releases an order for a compression spring. Chrome silicon, squared and ground ends, zinc plated, load tested at a specified height, packed to print. Four weeks out. The order gets a promise date and a place on the schedule, and from that moment the shop is measured against a date that was set before anyone knew what the job would actually run into.
The wire is on order. The job sits on the schedule showing a coiler open Tuesday, and the wire arrives Thursday, because the promise date in the system was the mill’s promise date and nobody updated it when the mill slipped. The wire comes in, gets a receiving ticket, waits for incoming inspection, and waits again while somebody pulls the mill cert and confirms the tensile matches what the print calls out. None of that is work anyone would call production. All of it is time the order is in the building and not moving.